The realistic build schedule

MTJ Construction LLC — Residential wood-frame | mtjconstructionllc.com

Most wood-frame houses take seven to twelve months from permit application to certificate of occupancy, and that range is not a guess — it is the sum of phases with known durations. Plan review alone runs 2–10 weeks, framing a 2,000 sq ft shell takes a crew 2–4 weeks, and every phase ends at an inspection that must pass before the next one starts.

Typical durations and key measurements across a wood-frame build
Build stageTypical time or size
Permit plan review2–10 weeks
Foundation forms stripped24–48 hours after pouring
Concrete strength test28 days
Framing, 2,000 sq ft house2–4 weeks
Stud / truss spacing16 in / 24 in on centre
Drywall finishing3 coats, ~24 h apart
Warranty terms12 months / 10 years

Terms the schedule runs on

Plan review
The building department's examination of the permit set before issuance. It commonly takes 2–10 weeks and ends in approval or a correction list.
Rough-in
The stage where plumbing, electrical, and HVAC are installed inside open framing. Each rough-in is inspected before insulation and drywall bury it.
On centre (OC)
Spacing measured from the centre of one member to the centre of the next. Load-bearing studs sit 16 in (400 mm) OC; roof trusses commonly 24 in (600 mm) OC.
Cylinder test (ASTM C39)
The standard compressive-strength check for concrete: samples cast at the pour are lab-cured and crushed at 28 days to confirm the mix reached design strength.
Certificate of occupancy (CO)
The document issued after a passed final inspection that makes a new house legal to live in. Lenders and insurers typically require it.
Punch list
The written list of small defects and unfinished items compiled at walk-through. It clears during the workmanship warranty period, commonly 12 months.

The short answer: sum the phases, don't guess

A realistic total is seven to twelve months, built up phase by phase — never quoted as one number.

A build schedule is a chain, not a list. Each phase has a typical duration and a hard gate at the end — an inspection, a test result, or a sign-off — and the next trade cannot start until that gate opens. That is why realistic schedules are quoted as ranges with phase dates, not as a single move-in day.

The biggest single block is often not construction at all. Building-permit plan review commonly takes 2–10 weeks depending on the jurisdiction, and lots in flood or historic zones land at the long end because extra reviewers see the plans.

Once the permit issues, the physical build of a typical wood-frame house runs roughly five to eight months: foundation, framing, rough-ins, drywall, finishes, and the final inspection sequence. Weather, correction cycles, and material lead times decide where inside that range a given project lands.

From application to occupancy, in order

Boundaries shift with jurisdiction, weather, and correction cycles; the order of the gates does not.

Weeks 1–10Permit application and plan review run their 2–10 week window; correction cycles and flood- orhistoric-zone review push toward the long end.Weeks 11–14Excavation, footings, and foundation pour; forms come off 24–48 hours later and cylinders go tothe lab for the 28-day ASTM C39 test.Weeks 15–18Framing the 2,000 sq ft shell — studs 16 in on centre, trusses 24 in on centre — then sheathing,windows, and roofing to dry-in.Weeks 19–24Plumbing, electrical, and HVAC rough-ins, each inspected before insulation and drywall close thewalls.Weeks 25–32Drywall finishing in three coats a day apart, interior finishes, final inspection, and thecertificate of occupancy.
Timeline: 5 dated entries

Permits first: the 2–10 week gate

Nothing physical starts until the building department finishes plan review, and the review clock runs only on a complete application.

Plan review commonly takes 2–10 weeks. The spread is jurisdiction: a small county office may turn a simple house in two weeks, while a large city routes the set through building, zoning, energy, and stormwater reviewers in sequence. Flood-zone and historic-district lots add specialized review and reliably sit at the long end.

Most applications do not pass on the first submission. Reviewers issue correction comments — missing shear-wall details, undersized headers, incomplete energy forms — and each resubmittal goes back into the queue, adding days or weeks per cycle.

The practical move is to treat review as a phase with its own schedule: submit a complete set, answer corrections within days, and book the excavation crew for the week after expected issuance rather than the week after submission.

  • Step 1 — Assemble the set: architectural plans, site plan, structural details, energy compliance forms
  • Step 2 — Submit; the review clock starts at acceptance of a complete application, not at drop-off
  • Step 3 — Answer correction comments; each resubmittal re-enters the queue
  • Step 4 — Permit issuance: the job card goes on site and inspection scheduling opens
  • Step 5 — Keep the permit alive: request inspections on schedule, since permits lapse when work stalls
The signature mark of this site, drawn as a plate

Foundation and framing: the measured weeks

Concrete is stripped in 24–48 hours but proven at 28 days; the frame above it takes a crew 2–4 weeks.

Foundation concrete is usually stripped of forms 24–48 hours after pouring, and backfill follows shortly after. Design strength, though, is verified on lab-cured cylinders crushed at 28 days to ASTM C39 — a paperwork gate that runs in parallel with construction instead of holding it up.

Framing a 2,000 sq ft (186 m2) wood-frame house typically takes a crew 2–4 weeks before mechanical rough-ins start. Load-bearing studs go in 16 in (400 mm) on centre, roof trusses commonly sit 24 in (600 mm) on centre, and sheathing, windows, and roofing follow directly behind the frame.

These two phases lock in the geometry every later inspection checks. Habitable rooms must finish at 7 ft (2.1 m) ceilings — sloped ceilings may drop to 6 ft 8 in over half the floor — and bedroom windows are roughed to open to at least 5.7 sq ft (0.53 m2) with sills no higher than 44 in (1,120 mm).

The signature mark of this site, drawn as a plate

The schedule in numbers

Typical durations and key measurements across a wood-frame build
Build stageTypical time or sizeWhat it means in practice
Permit plan review2–10 weeksLonger where the lot sits in a flood or historic zone
Foundation forms stripped24–48 hours after pouringWork continues while strength keeps building
Concrete strength test28 daysLab-cured cylinders crushed to ASTM C39 confirm design strength
Framing, 2,000 sq ft house2–4 weeksShell complete before mechanical rough-ins begin
Stud / truss spacing16 in / 24 in on centre400 mm for load-bearing studs; 600 mm for common roof trusses
Drywall finishing3 coats, ~24 h apartThree drying days before paint or texture
Warranty terms12 months / 10 yearsWorkmanship coverage versus structural coverage
Typical durations and key measurements across a wood-frame build

Sources and standards

Figures on this page reflect the International Residential Code, ASTM C39 testing practice, and standard industry warranty terms rather than any single builder's records.