MTJ Construction LLC — Residential wood-frame | mtjconstructionllc.com
Inspections run in a fixed order because each trade buries the last one's work — six gates from footing to final.
The footing and foundation inspection happens before the pour. The inspector verifies footing depth and bearing on undisturbed soil, rebar size and placement, and formwork dimensions; typical rejections are missing or misplaced rebar and footings resting on loose fill. After the pour, forms come off in 24–48 hours and the 28-day ASTM C39 cylinders go to the lab.
The framing inspection follows the shell. Inspectors check stud spacing — 16 in (400 mm) on centre for load-bearing walls — header sizes, hold-downs and connectors, and rough openings for bedroom egress windows, which must ultimately open to 5.7 sq ft (0.53 m2) of clear area with sills no higher than 44 in (1,120 mm). Typical rejections: over-notched or over-bored studs and missing metal connectors.
On narrow screens, swipe or scroll the plate sideways.
Rough-in inspections come next, one per trade. Electrical is checked for cable protection and box fill, plumbing is verified by pressure test, and mechanical is checked for duct sealing and combustion air; the walls stay open until all three pass. Typical rejections: cables bored too close to a stud edge without nail plates, leaking joints, and missing or undersized venting.
Insulation is inspected before drywall closes the cavities — typical rejections are gaps and compressed batts around windows and outlets. Drywall then runs three coats of joint compound with roughly 24 hours of drying between coats, and no inspection compresses that.
The final inspection covers the whole house: ceiling heights of 7 ft (2.1 m) in habitable rooms — sloped ceilings may drop to 6 ft 8 in over half the floor — smoke and carbon-monoxide detectors, GFCI protection, handrails and guards, and the egress windows as trimmed out. A pass issues the certificate of occupancy. How these gates fit the calendar is summed in House Construction Timeline by Phase.
Further reading